| The Project |
Water ingress through the structure into computer and electrical installation rooms was causing down time and risk to operations.
Pell Fishmann approached TAM to enquire about possible solutions to continuous water ingress problems in areas of the Marble Arch station. Water ingress through utility rooms had been occurring for some years causing increasing levels of degradation to the structure. |
| The Challenge |
Water ingress had been gradually permeating through the underground structure into computer and electrical installation rooms causing down time and risk to operation. |
| The Solution |
Pell Fishmann approached TAM to enquire about possible solutions to continuous water ingress problems to areas of Marble Arch station. Water ingress through utility rooms had been occurring of some years causing degradation to the structure. |
| TAM Contributory Success Factors |
TAM’s contribution
- Expertise and knowledge of these type of structures and leaking issue
- Technically advanced materials
- Problem diagnostic and consulting input
- Application techniques to get successful results
- We brought a competent solution for the Consultant
|
| Project Outcome |
Through the use of chemical injection with TAM products, the areas of leakage were sealed creating a dry working environment and ceasing further degradation of the asset. |
| Client Comment |
“I found TAM to be highly knowledgeable and supportive in dealing with our challenge. TAM's service was excellent throughout the project and their combination of reliable product knowledge and technical expertise ensured we had a successful outcome to this project”
Anca Pudwell - Pell Fishmann Group
|
|

|
| |
 |
|
|